In the Netherlands a BESS pays back on the monthly power peak and where the grid is congested

There are no regulated time-of-use bands: on medium voltage the DSO bills the highest quarter-hour peak of each month (kW-max) on top of contracted capacity, about €68 per kW a year if the peak recurs every month. Large parts of the grid are congested and new capacity may be refused or queued, so a battery that keeps offtake and feed-in within the available capacity also works as an alternative to a bigger connection.

96.9 €/MWhaverage day-ahead priceSMARD Großhandelspreise · 2025-09-01..2026-08-31
111 €/MWhdaily 4-hour spread
490hours at zero or negative price
€68/kW/yearMV power charge with the same peak every monthLiander, Stedin, Enexis · 2026

Prices over the last year

Monthly average day-ahead price, €/MWh. Real history, no forecast.

78
82
94
88
108
93
99
85
95
110
106
125
SeptOctNovDecJanFebMarAprMayJunJulAug

Average daily spread

1262 hours
1114 hours
848 hours

€/MWh: mean of the N most expensive hours minus the N cheapest of each day.

For commercial and industrial sites

No statutory time bands: the energy price and MV transport tariffs are flat, and normal/low (normaal/dal) pricing is a supplier choice. Only low-voltage connections up to 50 kW pay a high/low transport rate (high Mon-Fri 07-23, low at other hours and on public holidays), while energy tax falls by annual consumption bracket, from 0.09161 to 0.0031 €/kWh.

No statutory time bands: network charges are the same in every hour.

Power charge

On MV the customer pays contracted capacity (about €2.0-2.4 per kW a month) and kW-max, the highest quarter-hour offtake of each month (about €3.1-3.7 per kW a month): on average €68.19/kW/year across the three main DSOs, against €17.44/kW/year on LV up to 50 kW. Contracted capacity cannot be lowered within 12 months of an increase.

Value of exported energy

Over the last year solar captured 0.612 times the average day-ahead price, about €59/MWh against €96.9/MWh (Barrel estimate, Utrecht profile). Feed-in pays no transport tariff, but large consumers have no net metering (saldering), which ends for small consumers on 31 December 2026.

PV yield

1,015Noord
986 – 1,045
1,020Midden
1,013 – 1,025
1,050Zuid
1,024 – 1,072

kWh/kWp per year, PVGIS 5.3, 30° tilt, south, 14 % losses.

For utility-scale storage

Revenue streams open to a storage plant and their status.

SDAC and SIDC arbitrageactive

Single bidding zone; 15-minute day-ahead since 1 October 2025, average 4-hour daily spread of €110.75/MWh over the last year.

FCRactive

TenneT procures FCR in the common European auction; batteries eligible after prequalification, prices not loaded.

aFRRactive

TenneT aFRR capacity and energy bids are open to batteries; prices not loaded.

Passive imbalanceactive

Single-price imbalance settlement allows reacting in real time; revenue depends on the BRP or aggregator contract.

Congestion and non-firm contractsactive

Time-duration transport right at TenneT (at least 85 % of hours, tariff up to 65 % lower) and time-block right at regional DSOs since 1 April 2025; GOPACS and CBC contracts.

Energy tax relief for storageactive

Since 2022 supply to storage at a large-consumer connection can be exempt under conditions (secondary source, to be checked).

Capacity marketabsent

Energy-only market: no capacity mechanism as of 1 October 2026.

Rules

Summary of public rules. It does not replace the check of a qualified professional on the specific project.

Grid codedraft

Netcode elektriciteit chapter 3 (RfG) also applies to storage: type A below 1 MW with an equipment certificate, type B from 1 to 50 MW with an ESM document per module. The certificate is issued against NEN-EN 50549-1 (LV) or -2 (MV), taken from a secondary source: draft.

Connection and congestionverified

Where the grid is full, new capacity may be refused or queued; ACM introduced alternative transport rights (time-block and time-duration) and capacity-limiting contracts remain. In congestion areas an overrun is not automatically turned into a higher contract.

Registrationdraft

Batteries up to 1 MW are registered at energieleveren.nl; larger ones are notified directly to the DSO or TenneT and included in the connection and transport agreement (ATO). Partly secondary source.

Storage definitiondraft

The Energiewet has been in force since 1 January 2026, replacing the Elektriciteitswet 1998; the Netcode applies the generation-module rules to storage. The Netcode text itself was not consulted directly: draft.

Fire safetydraft

Guideline PGS 37-1:2023 covers lithium systems above 20 kWh and is applied today through the duty of care and case-by-case rules; legal anchoring is announced for 2027 or 2028, date uncertain. 10 m to the boundary or buildings, 5 m with a 30-minute enclosure, no distance with 60 minutes.

Taxverified

Corporate tax 19 % up to €200,000 of profit and 25.8 % above; VAT 21 %. The 2026 EIA allows a 40 % deduction for batteries on the Energielijst, to be notified to RVO within 3 months.

Products that can be used

A product is usable in the Netherlands if it declares NEN-EN 50549-1 (LV) or EN 50549-2 (MV) certification; from 1 MW an ESM document per module is also required. List of systems in the barrel.center comparator that declare the country's grid code: in preparation.

Sources and data status

DataSourceDateStatus
Prices, spreads, negative hoursSMARD Großhandelspreise, filter 256 (Niederlande), region DE-LU, quarter-hour resolutiondownloaded 2026-10-01verified
Regulated chargesLiander tarieven 2026 grootverbruik2026-01-01verified
PV yieldPVGIS v5.3 (EU JRC) PVcalc APIqueried 2026-10-01verified
Grid codeNetbeheer Nederland, Electricity Storage Modules compliance verification type A-D v2.02024-03, accessed 2026-10-01draft
Fire safetyPGS 37-1 gap analysis (Omgevingsdienst Zuid-Holland Zuid publication, quotes PGS 37-1:2023 v1.0 measures)2025-04-17draft

Data from the public sources cited. 'Verified' means a primary source, 'draft' a secondary source or a rule not read in full. Not advice: a project needs the site's and the contract's data.

A site to assess?

With the customer's load curve, Barrel's BESS connector simulates the site hour by hour, sizes the battery and prepares the offer under your brand.

Calculate the offer